Tiznit Laayoune Expressway
Articles
-
Morocco Secures $227 Million Loan for Tiznit-Dakhla Express Road Project
20 June 2019, by Said -
Morocco’s Southern Expressway Project Reaches 41% Completion, Boosting Regional Development
20 February 2021, by JérômeThe project, which is part of the new development model for the southern provinces of the kingdom, particularly between Tiznit and Laâyoune, has already exceeded 41% completion, said Yassine Zitoune, during a press conference during an inspection visit of the Sidi Ifni section by the governor of the province of Sidi Ifni, El Hassan Sidki. Regarding the section between Guelmim and Zrouila, the work has been completed. Between Tiznit and Sidi Bouadli, the work has reached 70% and exceeded 53% (…)
-
Morocco’s $1 Billion Tiznit-Dakhla Expressway Nears 75% Completion
6 November 2022, by PrinceThe project to build the expressway connecting Tiznit to Dakhla (1,055 km), at a total cost of around 10 billion dirhams, has already reached an execution level of more than 75%.
The completion rate of this mega project was around 72% in February, the project director had announced during a field visit by a delegation from the Interior, Territorial Authorities and Infrastructure Commission to the House of Advisors. The N1 national road between Laâyoune and Dakhla, which is a component of (…) -
Morocco’s Tiznit-Dakhla Expressway Project Nears Reality, Boosting Southern Economic Development
24 July 2020, by GinetteThe Tiznit-Dakhla expressway, the subject of a partnership agreement signed in 2015, will soon be a reality. This is a large-scale project that could strengthen the economic complementarity between the regions of the South and Souss-Massa.
This agreement was signed on the occasion of the commemoration of the 40th anniversary of the Green March, as part of the new development model for the southern provinces. It aims to give impetus to the relations between the southern provinces and the (…) -
Morocco Nears Completion of Tiznit-Dakhla Expressway in Southern Region
18 February 2022, by Armel -
Morocco’s Tiznit-Dakhla Expressway Nears Completion, Key Section 80% Finished
8 February 2022, by ArmelThe work on the Tan-Tan to Laâyoune section, included in the construction of the Tiznit-Dakhla expressway, is 80% complete.
Questioned about the progress of the construction site by Le360, Yassine Ansir, head of the engineering structures department in charge of this project, indicated that the work as a whole is progressing at a sustained pace.
"The road connecting Tan-Tan to Laâyoune over a distance of 220 km, which is part of the southern part of the project, has an overall progress (…) -
Major Moroccan Expressway Project Nears Completion, Linking Tiznit to Dakhla
20 February 2022, by ArmelThe work on the expressway connecting Tiznit to Dakhla, spanning 1055 km, has reached 72%, according to the Director of this gigantic project. As for the Laâyoune-Sakia El Hamra section, its completion rate has exceeded 80%.
In detail, the progress of the project is distributed as follows: 66% for the expressway, 71% for the major engineering structures and 100% for the development of the National Road N°1 between Laâyoune and Dakhla, specified the Director, Mbarek Fancha, on the occasion (…) -
Major Moroccan Highway Project Nears Completion: Tiznit-Dakhla Expressway 80% Done
19 September 2022, by GinetteThe construction work on the expressway connecting Tiznit to Dakhla is progressing rapidly. The photos of the work would be around 80% complete today.
This project, which covers a distance of 1,055 km, has already reached a completion rate of 78%. This is the result of an agreement signed in 2015 between the Ministry of the Interior, the Ministry of Economy and Finance and the Ministry of Equipment and four regions for a budget of nearly 10 billion dirhams. According to Mbarek Fancha, (…) -
Morocco’s 1,055 km Tiznit-Dakhla Expressway Nears Completion, 85% Done
26 May 2023, by SaidWhile it was scheduled to be completed in 2021, the Tiznit - Dakhla expressway should finally be completed next year. According to the Ministry of Equipment and Water, its completion rate is currently 85%.
This gigantic construction site, 1055 km long, is the result of an agreement signed in 2015 between the Ministry of the Interior, the Ministry of Economy and Finance and the Ministry of Equipment and four regions for a budget of nearly 10 billion dirhams.
Composed of the (…) -
Major Moroccan Highway Project Nears Completion: Tiznit-Dakhla Expressway 98% Done
3 August 2023, by PrinceThe Tiznit-Dakhla expressway will soon be delivered. The work has reached an execution level of 98% in the Laâyoune-Sakia El Hamra region and is fully completed on the Laâyoune-Tarfaya section.
At a total cost of 529 million dirhams (MDH), the 97-kilometer Laâyoune-Tarfaya section is fully completed. In the Laâyoune-Sakia El Hamra region, the work is already 98% completed, compared to 95% for the 116-kilometer Tarfaya-Oued El Waar section, at a cost of 608 MDH, reports the daily Al (…)