Morocco Accelerates Highway Expansion During Low Traffic Period

Autoroutes du Maroc (ADM) is taking advantage of the confinement period, where traffic is fluid, to accelerate the construction and maintenance of highway infrastructure.
This involves the widening of the lanes of the Casablanca-Berrechid and Casablanca bypass highways. The railway bridge of the Casablanca-Berrechid highway will also be restored. On this site, "ADM has taken advantage of the drop in traffic to be able to carry out the very complex transport of the metal elements of one of the two bridges, the work on which is 90% completed." The same applies to the maintenance work on the Rabat-Kenitra axis.
According to the same source, the fluidity of traffic has made it possible to "schedule the work at the Dar As-Sikkah interchange to minimize the disturbance at this very busy node under normal circumstances. This period also coincides with the maintenance of the Meknes-Fez axis".
Related Articles
-
Royal Air Maroc Leases Two Boeing 737-8 MAX Jets to Expand Fleet
5 June 2025
-
Cash Crunch Fears Grip Morocco Ahead of Eid al-Adha Bank Holiday
5 June 2025
-
EasyJet Resumes Toulouse-Marrakech Flights, Expands Winter Routes
4 June 2025
-
Moroccan Bus Fares Surge Ahead of Eid al-Adha, Sparking Union Outcry
4 June 2025
-
Moroccan Avocado Exports Surge to Record High, Defying Drought Concerns
4 June 2025