Noor Midelt I construction set to begin in January 2027 after seven-year delay

After seven years of waiting, Noor Midelt I has a new construction schedule. A Chinese tender published on November 18 calls for work to begin on January 15, 2027, and be completed on July 15, 2028, giving the major Moroccan solar project an 18-month construction period.

By Said A.
Noor Midelt I construction set to begin in January 2027 after seven-year delay

These dates appear in a China Energy International Group procurement notice for AIS electrical equipment. The notice, reproduced by the Chinese platform Yifangbao, details the specifications of the complex located in Midelt: 632,853 megawatt-peak of photovoltaic panels and 1 323,96 megawatt-hours of battery storage.

The document sets the construction period from January 15, 2027, to July 15, 2028. The tender for the electrical equipment is open from November 18 to 21.

The schedule comes two months after the announcement that Noor Midelt I was back on track with a Chinese consortium. China Energy officially announced in September that it had signed the construction contract on August 27 for the plant, whose design has been completely overhauled.

Initially awarded in 2019 to a consortium led by EDF Renewables, the project was to combine photovoltaic solar power with concentrated solar power technology. Disagreements over the latter delayed construction before a battery-based solution was adopted.

Equipment orders are now taking shape. Another Chinese notice, published on November 12, concerns the main transformers for Noor Midelt I.